This project was a 1000m2 full warm Bauder torch on system. Partial strip, 4-layer system, laying over 4000m2 of material. 26 New skylights, New fume & flue vents installed to replace the old. New cavity trays, among other minor details.

We braved a harsh winter and new year to complete this one in July 2024. A squad of 3-6 men travelled daily to and from Ulverston to bring this one together.

Complete for Cumbria Education Trust.